Current Construction / Road Closures

Madison County Projects

The Madison County Highway maintenance crews work continuously throughout the County. Most maintenance performed usually lasts no longer than one or two days. However, from time to time, maintenance or construction projects require an extended amount of time to complete. Listed below are only those projects where construction work will be on-going for a period of weeks.

Christmasville Road Repair Update

 ( Updated 10 / 23 / 2020 )

  • Surveying Complete
  • Engineering Design Complete
  • Construction Project Bids opened 9 / 23 / 2020
  • General Aquatic Resources Alteration Permit (ARAP) for the Construction and Removal of Minor Road Crossings (TDEC) received 9 / 29 / 2020
  • Project Awarded to Ford Construction Co., Inc. 10 / 7 / 2020
  • State Aid Project Funding – Approved 10 / 13 / 2020
  • Right-Of-Way Acquisition Process – Ongoing
  • Utilities Conflict Coordination/Relocation – Ongoing

Estimated Construction Start – End of October 2020

Estimated Construction End – Mid January 2021

Estimated start and end dates contingent upon weather, material availability and contractor scheduling.




LocationDescriptionStatusTime Frame
Christmasville Rd (between Oakfield
Road and Watson Road)
Crossdrain replacement
and headwall construction
ClosedCompletion Estimated
Mid January 2021


More Information

To inquire further information regarding these projects or other conditions, please contact the Highway Department at (731) 422-1651 or contact us.